Illinois Urban Manual
PRACTICE STANDARD
Temporary Stream Crossing
(no.)
CODE 975
Back to
Table of Contents

(Source:
Kane-DuPage Soil and Water Conservation District - Illinois)
DEFINITION
A bridge, ford, or temporary structure installed across a
stream or watercourse for short-term use by construction vehicles or heavy
equipment.
PURPOSE
The purpose of this practice is to provide a means for
construction vehicles to cross streams or watercourses without moving sediment
into streams, damaging the streambed or channel, or causing flooding.
CONDITIONS WHERE PRACTICE APPLIES
Where heavy equipment must be moved from one side of a stream
channel to another, or where light-duty construction vehicles must cross the
stream channel frequently for a short period of time. Generally, a temporary
stream crossing is applicable to flowing streams with drainage areas less than 1
square mile. More exacting engineering methods should be used on larger drainage
areas.
CRITERIA
In addition to erosion and sediment control, structural
stability, utility, and safety must also be taken into consideration when
designing temporary stream crossings. Bridge designs in particular, should be
completed by a qualified engineer.
The anticipated life of a temporary stream crossing structure
is usually considered to be 1 year or less. Remove the structure immediately
after it is no longer needed.
As a minimum, design the structure to pass bank full flow or
peak flow, whichever is less, from a 2-year frequency, 24-hour duration storm
without over topping. Ensure that no erosion will result from the 10-year peak
storm.
Ensure that design flow velocity at the outlet of the crossing
structure is non-erosive for the receiving stream channel.
Consider overflow for storms larger than the design storm and
provide a protected overflow area.
A water diverting structure such as a swale shall be
constructed (across the roadway on both roadway approaches) 50 feet maximum on
either side of the waterway crossing. This will prevent roadway surface runoff
from directly entering the waterway. The 50 feet is measured from the top of the
waterway bank. If the roadway approach is constructed with a reverse grade away
from the waterway, a separate diverting structure is not required.
The aggregate for the roadway shall be a minimum of 6 inches
thick stone or recycled concrete meeting one of the following IDOT coarse
aggregate gradations: CA-1, CA-2, CA-3 or CA-4.
The aggregate will be placed on geotextile fabric meeting the
requirements in material specification 592 GEOTEXTILE Table 1 or 2, class I, II,
or IV.
CONSIDERATIONS
Careful planning can minimize the need for stream crossings.
Try to avoid crossing streams, whenever possible, complete the development
separately on each side and leave a natural buffer zone along the stream.
Temporary stream crossings are a direct source of water pollution; they may
create flooding and safety hazards; they can be expensive to construct; and they
cause costly construction delays if washed out.
Select locations for stream crossings where erosion potential
is low. Evaluate stream channel conditions, overflow areas, and surface runoff
control at the site before choosing the type of crossing. When practical, locate
and design temporary stream crossings to serve as permanent crossings to keep
stream disturbance to a minimum.
Plan stream crossings in advance of need, and when possible,
construct them during dry periods to minimize stream disturbance and reduce
cost. Ensure that all necessary materials and equipment are on-site before any
work is begun. Complete construction in an expedient manner and stabilize the
area immediately.
When construction requires dewatering of the site, construct a
bypass channel before undertaking other work. If stream velocity exceeds that
allowed for the in-place soil material, stabilize the bypass channel with riprap
or other suitable material. After the bypass is completed and stable, the stream
may be diverted.
Unlike permanent stream crossings, temporary stream crossings
may be allowed to overtop during peak storm periods. However, the structure and
approaches should remain stable. Keep any fill needed in floodplains to a
minimum to prevent upstream flooding and reduce erosion potential. Use riprap to
protect locations subject to erosion from overflow.
Where appropriate, install in-stream sediment traps
immediately below stream crossings to reduce downstream sedimentation. When
used, excavate the basin a minimum of 2 feet below the stream bottom and
approximately two times the cross-sectional flow area of the existing channel.
Ensure that the flow velocity through the basin does not exceed the allowable
flow velocity for the in-place soil material; otherwise it should not be
excavated. In locations where trees or other vegetation must be removed, the
sediment trap may be more damaging to the stream than if it was not installed.
Stream crossings are of three general types: bridges, culverts
and fords. Consider which method best suits the specific site conditions.
Bridges - Where available materials
and designs are adequate to bear the expected loading, bridges are preferred for
temporary stream crossing.
Bridges usually cause the least disturbance to the streambed,
banks, and surrounding area. They provide the least obstruction to flow and fish
migration. They generally require little or no maintenance, can be designed to
fit most site conditions, and can be easily removed and materials salvaged.
However, bridges are generally the most expensive to design and construct.
Further, they may offer the greatest safety hazard if not adequately designed,
installed, and maintained, and if washed out, they cause a longer construction
delay and are more costly to repair.
In steep watersheds it is recommended to tie a cable or chain
to one corner of the bridge frame with the other end secured to a large tree or
other substantial object. This will prevent flood flows from carrying the bridge
downstream where it may cause damage to property.
Culvert crossings - Culverts are the
most common stream crossings. In many cases, they are the least costly to
install, can safely support heavy loads, and are adaptable to most site
conditions. Construction materials are readily available and can be salvaged.
However, the installation and removal of culverts causes considerable
disturbance to the stream and surrounding area. Culverts also offer the greatest
obstruction to flood flows and are subject, therefore, to blockage and washout.
Fords - Fords made of stabilizing
material such as rock are often used in steep areas subject to flash flooding,
where normal flow is shallow (less than 3 inches deep) or intermittent. Fords
should only be used where crossings are infrequent. Fords are especially adapted
for crossing wide, shallow watercourses.
When properly installed, fords offer little or no obstruction
to flow, can safely handle heavy loading, are relatively easy to install and
maintain, and, in most cases, may be left in place at the end of the
construction.
Problems associated with fords include the following: 1)
approach sections are subject to erosion. Generally do not use fords where bank
height exceeds 5 feet, 2) excavation for the installation of the riprap-gravel
bottom and filter material causes major stream disturbance. In some cases, fords
may be adequately constructed by shallow filling without excavation, 3) the
stabilizing material is subject to washing out during storm flows and may
require replacement, 4) mud and other contaminants are brought directly into the
stream on vehicles unless crossings are limited to no flow conditions.
PLANS AND SPECIFICATIONS
Plans and specifications for temporary stream crossing shall
be in keeping with this standard and shall describe the requirements for
applying the practice to achieve its intended purpose. At a minimum include the
following items:
- The location of the crossing.
- Required material specifications.
All plans shall include the installation, inspection, and
maintenance schedules with the responsible party identified.
Standard drawing IL-675 TEMPORARY STREAM CROSSING PLAN may be
used as the plan sheet.
OPERATION AND MAINTENANCE
Inspect temporary stream crossings after runoff-producing
rains to check for blockage in channel, erosion of abutments, channel scour,
riprap displacement, or piping. Make all repairs immediately to prevent further
damage to the installation.
Remove temporary stream crossings immediately when they are no
longer needed. Restore the stream channel to its original cross-section, and
smooth and appropriately stabilize all disturbed areas.
Leave in-stream sediment traps in place to continue capturing
sediment.
NRCS IL
August 1994
< Back to Table of Contents
|