DEFINITION
A temporary pit which is constructed to trap and filter water
for pumping into a suitable discharge area.
PURPOSE
The purpose of this practice is to remove excessive water from
excavations in a manner that improves the quality of the water being pumped.
CONDITIONS WHERE PRACTICE APPLIES
Sump pits are constructed when water collects during the
excavation phase of construction. This practice is particularly useful in urban
areas during excavation for building foundations.
CRITERIA
A perforated vertical standpipe is placed in the center of the
pit to collect filtered water. The standpipe will be a perforated 12 to 24-inch
diameter corrugated metal or PVC pipe. Water is then pumped from the center of
the pipe to a suitable discharge area. The pit will be filled with coarse
aggregate meeting the requirements of IDOT standards for gradations of CA-2,
CA-3 or CA-4.
CONSIDERATIONS
Discharge of water pumped from the standpipe should be to a
suitable practice such as practice standard IMPOUNDMENT STRUCTURE-ROUTED
842, PORTABLE SEDIMENT TANK 895,
TEMPORARY SEDIMENT TRAP
960, or a stabilized area.
If water from the sump pit will be pumped directly to a storm drainage system,
filter fabric will be wrapped around the standpipe to ensure clean water
discharge. The fabric, if used, shall meet the requirements as shown in material
specification 592 GEOTEXTILE Table 1 or 2 class 1 with an equivalent opening
size of at least 30 for non-woven or 50 for woven. It is recommended that 1/4 to
1/2 inch hardware cloth wire be wrapped around and secured to the standpipe
prior to attaching the filter fabric. This will increase the rate of water
seepage into the standpipe.
PLANS AND SPECIFICATIONS
Plans and specifications for installing and utilizing sump
pits shall be in keeping with standard and shall describe the requirements for
applying the practice to achieve its intended purpose.
The contractor or responsible reviewing authority will
determine the number of sump pits and their locations.
Standard drawing IL-650 SUMP PIT PLAN may be used as a plan
sheet.
All plans shall include the installation, inspection, and
maintenance schedules with the responsible party identified.
OPERATION AND MAINTENANCE
The sump pit may have to be replaced if the pit and filter
fabric plugs with sediment.