DEFINITION
A small rock dam constructed across a grassed swale or road ditch.
PURPOSE
The purposes of this practice are to reduce the velocity of concentrated
stormwater flows, thereby reducing erosion of the swale or ditch, trap sediment
generated from adjacent areas or the ditch itself and to increase infiltration
when suitable soils are present.
CONDITIONS WHERE PRACTICE APPLIES
This practice, utilizing a combination of rock sizes, is limited to use in
small grassed swales or open channels that drain 10 acres or less. It shall not
be used in a perennial stream where protection of the flowing stream is the
objective.
Some specific applications include:
- Temporary ditches or swales that, because of their short time of service,
cannot receive a non-erodible lining but still need protection to reduce
erosion
- Permanent ditches or swales that cannot receive a permanent non-erodible
lining for an extended period of time
- Either temporary or permanent ditches or swales that need protection
during the establishment of grass linings
- An aid in the sediment trapping strategy for an active construction site.
This practice is not a substitute for major perimeter trapping measures such
as practice standard TEMPORARY SEDIMENT TRAP 960.
CRITERIA
The drainage area of a ditch or swale being protected shall not exceed 2
acres when rock meeting IDOT CA-1, CA-2, CA-3 or CA-4 gradation is used alone
and shall not exceed 10 acres when rock meeting IDOT RR-3 or RR-4 gradation and
Quality Designation A is added on the downstream side of the dam.
The maximum height of the rock check dam shall be 3.0 feet. The top of the
rock check dam shall be a minimum of 1.0 feet below the top of the ditch or
swale.
The maximum spacing between the dams should be such that the toe of the
upstream dam is at the same elevation as the top of the rock at the center of
the downstream dam.
The rock check dams shall be placed such that the resultant ponding will not
cause inconvenience or damage to adjacent areas or structures.
The center of the rock check dam shall be at least 6 inches lower than the
sides. Hand or mechanical placement will be necessary to achieve complete
coverage of the ditch or swale and to assure that the center of the dam is lower
than the sides. Rock shall be placed according to
construction specification 25 ROCKFILL
using Method 1 placement and Class III compaction.
CONSIDERATIONS
For added stability, the base of the rock check dam should be keyed into the
soil to a depth of 6 inches.
Filter fabric may be used under the rock to provide a stable foundation and
to facilitate removal of the rock. The filter fabric shall meet or exceed the
requirements of material specification 592
GEOTEXTILE Table 1 or 2, Class I, II or IV.
Rock check dams are effective in reducing flow velocity and thereby the
potential for channel erosion. It is usually better to establish a protective
vegetative lining before flow is confined or to install a structural channel
lining than to install rock check dams. Field experience has shown rock check
dams to perform much more effectively than silt fences or straw bales in the
effort to stabilize "wet-weather" ditches.
Rock check dams installed in grass-lined channels may kill the vegetative
lining if submergence after rains is too long and/or siltation is excessive.
If temporary rock check dams are used in grass-lined channels that will be
mowed, care should be taken to remove all the rock when the rock check dam is
removed. This should include any rocks that have washed downstream.
Field experience has shown that many rock check dams are not constructed with
the center lower than the sides forming a weir. Stormwater flows are then forced
to the rock-soil interface, thereby promoting scour at that point and subsequent
failure of the structure to perform its intended function.
PLANS AND SPECIFICATIONS
Plans and specifications for installing rock check dams shall be in keeping
with this standard and shall describe the requirements for applying the practice
to achieve its intended purpose. At a minimum include the following:
- Location where the practice will be installed
- Dimensions, elevations, and spacing between the dams
- Rock gradation and quality
- Fabric specification if used
All plans shall include installation, inspection, and maintenance schedules
with the responsible person identified.
Standard drawing ROCK CHECK DAM IL-605CA
or IL-605R may be used as the plan sheet.
OPERATION AND MAINTENANCE
On active construction sites, the rock check dams shall be inspected at least
once every 7 days and within 24 hours of a rainfall of 0.5 inches or more. If
any erosion has taken place around or below the rock check dam or if rocks have
been dislodged, repairs shall be made to prevent further damage. Sediment shall
be removed once it has accumulated to one-half the height of the rock check dam.
The center of the rock check dam shall also be inspected periodically to insure
that the center of the dam is lower than the sides.
Unless they will be incorporated into a permanent stormwater management
control, rock check dams must be removed when their useful life has been
completed. In temporary ditches and swales, rock check dams should be removed
and the ditch filled in when they are no longer needed. In permanent structures,
rock check dams should be removed when a permanent lining can be installed. In
the case of grass-lined ditches, rock check dams should be removed when the
grass has matured sufficiently to protect the ditch or swale. The area beneath
the rock check dams should be seeded and mulched immediately after they are
removed.
For rock check dams that are made a part of a permanent stormwater management
control, regular inspections should be made to see if any erosion has occurred
around or below the dam and if any rock has been dislodged. Immediately make all
needed repairs to prevent further damage. If sediment trapping is to be a
continuing function of the rock check dam, the sediment shall be removed when it
has accumulated to one-half the depth of the rock check dam.
REFERENCES
Illinois Department of Transportation, 1997. Standard Specifications for Road
and Bridge Construction. IL
Virginia Department of Conservation and Recreation, Division of Soil and
Water Conservation, 1992. Virginia Erosion and Sediment Control Handbook, 3rd
ed., VA