Illinois Urban ManualPRACTICE STANDARDTemporary Sediment Trap
|
| Drainage Area (acres) | Weir Length (ft.) |
|---|---|
| 1 | 4.0 |
| 2 | 6.0 |
| 3 | 8.0 |
| 4 | 10.0 |
| 5 | 12.0 |
Dimensions shown are minimum.
The release rate of the basin shall be that rate required to achieve minimum detention times of at least 10 hours. The elevation of the permeable fill outlet shall be placed such that it only drains the dry detention storage.
Direct spillway bypass to natural, stable areas. Locate bypass outlets so that flow will not damage the embankment.
Discharges from both the principal and emergency spillways of a sediment trap must be conveyed to a natural waterway in a channel of adequate capacity and stability. Where this channel intersects with the natural waterway, the discharge shall be less than 1 1/2 feet per second or otherwise below the velocity which will initiate erosion or scour within the receiving waterway. Outlets to stormwater facilities must have adequate capacity to receive the discharge from the sediment trap.
Where an emergency spillway is utilized, the spillway crest elevation should be at least 1.5 feet below the settled top of the embankment with the emergency spillway crest being 0.5 feet below the top of the embankment.
Rock placement - The rock will be placed according to construction specification 25 ROCKFILL. Placement will be by Method 1 and compaction of rockfill will be Class III.
CONSIDERATIONS
Select locations for sediment traps during site evaluation. Note natural drainage divides and select trap sites so that runoff from potential sediment-producing areas can easily be diverted into the traps.
Make traps readily accessible for periodic sediment removal and other necessary maintenance. Plan locations for sediment disposal as part of trap site selection. Clearly designate all disposal areas on the plans.
In preparing plans for sediment traps, it is important to consider provisions to protect the embankment from failure from storm runoff that exceeds the design capacity. Consider non-erosive emergency spillway bypass areas, particularly if there could be severe consequences from failure. If a bypass is not possible and failure would have severe consequences, consider alternative sites.
Sediment trapping is achieved primarily by settling within a permanent pool formed by excavation, or by a combination of excavation and embankment. Sediment-trapping efficiency is a function of surface area and inflow rate. Installations that provide pools with large length to width ratios reduce short-circuiting and allow more of the pool surface area for settling. This optimizes efficiency.
The minimum length of flow through the trap should be 10 feet and the minimum length to width ratio should be 2:1. If site conditions permit a greater travel distance through the basin and greater length to width ratio the water quality benefit provided by the sediment trap will be enhanced. The average trap permanent pool depth should be a minimum of 3 feet to prevent re-suspension of sediments.
Another method of improving the trapping efficiency is to place geotextile fabric between the riprap and coarse aggregate. If this is done, timely maintenance is needed to assure that the outlet does not clog with sediment.
Because well-planned sediment traps are key measures to preventing off-site sedimentation, they should be installed in the first stages of project development.
PLANS AND SPECIFICATIONS
Plans and specifications for temporary sediment traps shall be in keeping with this standard and shall describe the requirements for applying the practice to achieve its intended purpose. At a minimum include the following items:
All plans shall include the installation, inspection, and maintenance schedules with the responsible party identified.
The standard drawing IL-660 TEMPORARY SEDIMENT TRAP may be used as the plan sheet.
OPERATION AND MAINTENANCE
Inspect temporary sediment traps after each period of significant rainfall. Remove sediment and restore the trap to its original dimensions when the sediment has accumulated to one-half the design depth of the permanent pool. Place the sediment that is removed in the designated disposal area and replace the contaminated part of the gravel facing.
Check the structure for damage from erosion or piping. Periodically check the depth of the spillway to ensure it is a minimum of 1.5 feet below the low point of the embankment to slightly above design grade. Any riprap displaced from the spillway must be replaced immediately.
After all sediment-producing areas have been permanently stabilized, remove the structure and all unstable sediment. Smooth the area to blend with the adjoining areas and stabilize properly.
REFERENCES
Illinois Department of Transportation, 1997. Standard Specifications for Road and Bridge Construction. IL
North Carolina Sedimentation Control Commission, 1988. Erosion and Sediment Control Planning and Design Manual. NC
Northeastern Illinois Planning Commission, 1991. Model Soil Erosion and Sediment Control Ordinance. IL
Northeastern Illinois Planning Commission, 1993. Urban Stormwater Best Management Practices for Northeastern Illinois. IL
Virginia Department of Conservation and Recreation, Division of Soil and Water Conservation, 1992. Virginia Erosion and Sediment Control Handbook. 3rd ed., VA
NRCS IL October 2001
urbst960.doc
|
|